A Guide to Implementing the Theory of Constraints (TOC)

PowerPoints

Preface

Introduction

Contents

Next Step

Advanced

 

Bottom Line

Production

Supply Chain

Tool Box

Strategy

Projects

& More ...

Healthcare

 

Project Buffers

Critical Chain

Implementation Details

Multi-Project Drums

 

 

 

 

Comparing Safety In Production & Projects

There are two groups of people who are likely to use these pages on projects; those with prior knowledge of production operations (manufacturing) and those with pure project backgrounds.  For this reason I want to compare and contrast between production operations and project operations.  The similarities are much greater than the differences.  I want to do this for two reasons;

1.    Provide a bridge for people with production operation experience in order to enter into the project domain.

2.    Show people with project operation experience that the challenges that they face are not that different from those experienced in production environments.

So I ask for your indulgence if you already feel slighted that “your” area of expertise is apparently no more difficult than “their” area of expertise.  You see, we are basically all in the same boat – and we are all at sea as well.  Industrialization is new.  We only have to check whether our parents’ generation ran projects or production operations as we do, and if they did, then check out our grand-parents generation.  The scale and scope of operations today is vastly different from that of just one or two generations ago.  For instance, just one generation ago we didn’t have computers to make mistakes quite as quickly as we are able to today.

In fact, computers are now so ubiquitous that we can discuss operations in terms of the software that drives them, or at least the generic approaches.  For production operations the first software was material requirements planning (mrp or small mrp – referring to the use of lower case letters).  Material requirements planning allowed the building of bills of material (BOMs) for a process; a list of all the bits and pieces and maybe the places where, and the time when, they were required.  It wasn’t long before this was beefed up to materials resources planning (MRP or MRP II) with the addition of capacity scheduling of each step in the routing that had been used to generate the bill of materials.  More recently this has been beefed up once again to enterprise resources planning (ERP) where schedules are wired across functions as well as within functions.  Sales and marketing now know what production is doing and vice versa (well it sounds good doesn’t it?)

The project operations equivalent of the mrp, MRP II, ERP, alphabet soup is Critical Path Method, (CPM for short).  Critical Path Method tends to be associated with the Gantt charts that are used to graphically present the relationships between tasks in a project, but it is generated from an approach called program evaluation and review technique (or PERT for short).  In fact, as we will soon see, program evaluation and review technique can be equally applied to production operations as well as to projects.  Indeed, maybe PERT is responsible for the two short comings of both MRP and CPM.  Both approaches assume, even today, that there is more capacity at each step in a production process, or task of a project, than is actually required.  Colloquially, we tend to call this “infinite capacity” although we only mean that there is “more than enough.”  Before the advent of computers when PERT was a manual exercise, this simplification made the impossible possible.

Also, both MRP and CPM assume that safety is localized throughout the respective operations.  In production operations, safety is localized in the queuing of product (work-in-process).  Each queue represents a safety buffer that allows late work to catch up to its schedule through the rearrangement of items or “jobs” in the queue.  Historically, these types of scheduling approaches originated in so-called job shop environments – places where machinery was likely to be grouped according to function, rather than the flow-shops that are so much more common in all but the smallest of facilities today.  In Critical Path Method the safety is localized not in the queue, but within each and every task in the project.

Assumptions of infinite capacity and the localization of safety throughout the operation are the two aspects that cause so much trouble to modern operations.  We won’t address the issues of infinite capacity assumptions until the next page on Critical Chain Project Management, because this is an important issue of itself and is to me the distinction between Critical Chain Project Management and Critical Path Method.  On this page we will address the issue of localized safety in each step or each task.  Essentially we are going to move from safety that is localized, specific, and everywhere, to safety that is general, aggregate, and located in just a few critical places.

Having safety “embedded” in each step of a production process or each task of a project ought, at first pass, seem to be an effective solution.  After all you can size each individual allocation as required – regardless of whether it is explicit within a production process queue, or implicit within a project task.  However, a number of operational and psychological factors contrive against us.  The operational factors are the dependent nature of serial operations and the inherent variability that occurs within each operation.  The psychological factors are varied, and probably more important for project-based operations than production-based operations.  We will deal with the psychological factors as we come to them.

In order to develop the argument for the aggregation and placement of buffers in project management, I am going to use a PERT diagram for both a production process and a project.  In order to do that we must make use of the realization that a project is an “A” plant tipped on its side.

Let’s look at this in more detail.

 
A Project Is An “A” Plant Tipped On Its Side

A project is an “A” plant tipped on its side (1).  This is the “thing” that finally allowed me to see the relationship between production operations and project operations and their buffers or safety.  But what is an “A” plant you are asking?  Theory of Constraints sees 4 generic flows in production operations, they are; “V” plants or divergent plants (divergent from the bottom of the “v” to the top), “A” plants or convergent plants (convergent from the bottom of the “a” to the top), “I” plants or linear plants, and “T” plants – a plant with a linear stem and an explosion of choices at the top (assembly).  Each type of plant is typical of particular operations.  “A” plants are typical of situations where a number of different components from different raw materials come together to form a final assembly.

Let’s draw a simple, a very simple, “A” plant on its side to see how it would look.

We have 6 steps in our simple process.  Step 1 must be done before step 2, and step 2 must be done before step 3.  Step 4 must be done before step 5, and steps 3 and 5 together must be done before the final step, step 6.  Two arms; steps 1-3 and steps 4-5 converge on step 6.

This type of logic diagram is common in Theory of Constraints.  The logic might coincide with the physical layout of the plant; more often than not, it won’t.  For an example of a more complex “A” plant logic diagram and its corresponding physical layout, have a look at the diagrams for the P&Q Question.

If we were to draw a very simple project, then apart from some different names, it would look exactly the same, lets see.

We have 6 tasks in our simple project.  Task 1 must be done before task 2, and task 2 must be done before task 3.  Task 4 must be done before task 5, and tasks 3 and 5 together must be done before the final task, task 6.  Two arms; tasks 1-3 and tasks 4-5 converge on task 6.

The logic diagram for production operations and project operations are exactly the same, save for different labels.  Let’s put the two diagrams side-by-side.

Of course they are the same, but from a project perspective something is wrong.  We really expect to see some proportionality between the tasks and the time taken, and moreover, we expect to see each task abut onto the next.  However, such a notion is frightening to production people because the time taken by each step is miniscule in the overall scheme of things.

Let’s draw each respective diagram so that the steps and tasks are somewhat proportional to the time taken.

That looks better from a project perspective.  However, from a production perspective the time shown, let’s call it the touch time, is still way too large.  The touch time as shown is something larger than 10% of the previous size for each task.  Reality is that it is more like 1-2% or maybe 5% at the absolute outmost.  Really just a sliver of a line.  You see, most things in most production operations spend an awful lot of time just waiting in queues.

Let’s have a look at this waiting in queues.

Waiting, waiting, waiting; the waiting in production operations is explicit.  It is in the queues that are planned into the process from the very beginning.  The actual touch time of material in the process is very small indeed.

This raises a question; there isn’t any waiting in projects – right?  Well, not explicitly, and it isn’t called waiting, it is called safety – “things” in production might wait but people in projects don’t like to be seen waiting, so we have to call it safety.

Let’s have a look.

It’s there alright, but it is “hidden” in the estimate of the task duration.

Having got this far (even if you really don’t think that there is any safety in projects what-so-ever), we can now show the apparent differences between buffering in production operations in Theory of Constraints and buffering in project operations in Theory of Constraints.  If buffering is an unfamiliar concept to you, then please wait a short while.  We need to bury the devil which says that buffering in the two approaches is different.  Once we have done that, then we can start all over again with the vexed question of why we even have buffers in project management.

Let’s start first with our “A” plant process.  What if we accept that we can move from an MRP schedule to a drum-buffer-rope (DBR) sequence.  In drum-buffer-rope the only things scheduled are the start and the finish (and maybe the drum but we will leave that out here).  If we accept that, then we can aggregate the touch time and we can aggregate the waiting time.  By aggregating the waiting time we make the total waiting time available to the whole process.

Let’s have a look.

Some clarity is needed.  We haven’t “squashed” steps 1, 2, and 3 together, as though we expect each of them to occur one after the other – bang, bang, bang; we simply say that sometime between step 1 and step 6 there will be a sequence of step 2 and then step 3.  We don’t know exactly when, but we are confident that it will occur within the total time allowed.

What happens next is that because the touch time in production operations is so small (remember we have drawn it here 1 to 5 to 10 times too large) it is ignored completely.

This is what our process looks like as a consequence.

Our production process looks as though the whole of the process lead time is occupied by the buffer.  We arrive at that simplifying action by ignoring the touch time.  Can we make a similar simplification for projects?  Well the historic answer is no!  The touch time is too large and too important to ignore.

What then if we accept that we can move from a Critical Path schedule to a Critical Chain sequence.  The only things scheduled being the start and the finish.  If we accept that, then we can aggregate the touch time and we can aggregate the safety time.  By aggregating the safety time we make the total safety time available to the whole process.

Let’s have a look.

Well that is almost correct.  In actuality there is one more step.  We must bunch-up tasks 1, 2 , 3, & 6.  Let’s see.

And if we do that, then we also have to “shift” tasks 4 & 5 back.  This looks as though we have made the project longer, however, we haven’t removed non-necessary safety yet – from either case.  In a short while we will look at the specifics for project operations.  Production operations has already been addressed in some detail on other pages.

Having made these changes, do you see the apparent difference between the two sets of buffers?  To me, the buffers in production operations appeared to occupy the whole of the process.  In project operations the buffers don’t occupy the whole of the project, instead they appear to be bunched-up towards the end.  However, the reality rather than the appearance is more important.  The reality is that the buffers in both cases are treated in exactly the same way, the only difference is that in one of the cases, production operations, we can make a simplifying assumption and remove the touch time from contention.  That is all that we have done that is different.

The exact mechanics in each case are a little different from this simple example.  We have dealt with the production operations case in detail in the production pages of this website, and we will deal with the detail of project operations case over the remainder of these project pages.  Although the detail may vary, the principle is the same (and in distribution and raw material supply as well); we wish to identify and locate all the locally distributed safety or waiting and aggregate it into one or several strategically placed global buffers where the least total safety can be of the greatest benefit to the system as a whole.  If we can remove safety that is embedded but wasted then we should be able shorten the duration of the project without endangering the on-time reliability of the completion date.  In fact, as we will see, we can substantially improve the reliability of the completion date as a consequence.

First, however, let’s consider a few more aspects of touch time and variability in production operations and projects.

 
Touch Time And Variability In Projects

The touch time in production operations is a very small part of the total time spent in the process; most of the time is, in fact, spent waiting.  In addition to the touch time being a small part of the total, there is also little variability in its duration.  This isn’t so much a case of the repeatability of the tasks, but rather the mechanization of the tasks – although, clearly, the more often a task is repeated the more likely we are to want to mechanize it.  And if we can mechanize it, then automation is the next logical step after that.  There are without doubt some manufacturing tasks which have greater variability in their touch time than others; those that use natural products and those that use manual labor are the two that spring to mind.  However, even in these cases the variability is still not large.

So where then is the variability in production operations?  It is in the wait or queue time?  In fact, it is an assertion.  I can’t quantify the assertion because I have never seen a graph of variability in wait time.  There is genuine concern about the amount of work-in-process and hence total wait time in a process, but little interest in its variability between the same steps for the same product.  Its an invisible attribute.

What then of projects?  Let’s start at the easy place.  Variability in wait time or safety time is said to not exist, because safety time is said not to exist, or at least insufficient safety time is said to exist because some tasks in projects, and certainly almost all whole projects, tend to be late rather than on-time or even early.  In the first instance then, it is better to view a project as a mirror image of a production process.  All the variability in a project appears to be in the touch time of the task.

Why should the touch time of a task be variable?  To answer that we have to look at two things;

§  The nature of the task

§  The nature of the resources (= people)

Let’s look at the nature of the task first, and let’s just limit ourselves for the time being to the realization that sometimes the subject matter of the task unfolds swimmingly well, and equally, sometimes it does not.  Thus there is some natural variability even if a particular task is well known and well practiced.

How about the nature of the resources then?  Just as in production operations, people add variability to a task as well; people unlike machines have good days and bad days (although I know a few machines that seemed to be able to mimic this attribute well).  If someone has not done a specific task before, or the task is significantly different from prior experience, then we ought to expect greater variability.  The task may take less time, it may take more.  People with a large amount of prior experience (both explicit and tacit knowledge) might turn out less variable results than someone who is new.  Let’s summarize this.

There is variability around what is known

Even if we confine ourselves to what is known within the task of a project, then there is variability.  Because the touch time is so large in proportion to the duration of the whole project, so too, is the effect of any variability.  In production operations the task variability is small, the tasks are small, and the shock absorbers for this, the in-queue waiting time, is huge.  In project operations in contrast, the tasks are large, the variability is therefore magnified, and the shock absorbers are perceived to be small to non-existent.

Let’s confine ourselves for the moment to just this simple view of task variation.  It is naive I know, but if we can understand the effects in this simple case, then the more complicated issues caused by uncertainty will fall out as a consequence.  We will address uncertainty, but not quite yet.  Let’s have a look at the effect of variability on dependent tasks in a simple project.

 
Variability And Dependent Events

Common sense would seem to suggest to us that variability in project tasks ought not to be such a bad thing.  Surely over a number of tasks the variability should average out?  Surely the larger the size of a project, and the number of individual tasks, the more likely it is that the project will come in on time as the over-runs and under-runs average out?

If this is our plan,

Then surely our reality might be something like this – well exactly like this.

That is how it should be.  Tasks that take longer than estimated are balanced out by tasks that take less than estimated and the overall project finishes on time.  Well, nice, if you can get it, but reality has a terrible habit of making the simple not-so-simple after all.  Let’s look at another possibility.

All that I did was shuffle the pack a bit and suddenly the shorter and longer task don’t cancel out any longer, and the consequence is a late finish.  Not very late of course, but still late.  The tasks didn’t cancel because there is a dependency between tasks 3 and 5; both must be completed before task 6 can begin.  Tasks 1 and 2 average out, but the gain in task 3 could not be transferred because we were still waiting for task 5 to finish.  Task 6 as it turns out was late but couldn’t take advantage of the saving in task 3, so the whole project was late.

Sad, is it not?  But it gets worse.  Let’s see.

As they say; “stuff happens” and this would seem to be a rather good example.  We might be tempted to claim that this is a special case – not the conspiracy of the longer completions grouping together by chance and the shorter completions grouping together by chance – but rather the consequence of the convergence or confluence or integration or assembly at task 6 of the “arm” of task 4 - task 5  and the “arm” of task 1 - task 2 - task 3.  There is a co-dependency between tasks 3 and 5.

Multiple dependency at convergences have quite an impact, but there are also other dependencies wherever there is a “hand-off” between two adjacent tasks.  We might not like to think of them in the same terms as the convergence, but alas, the mechanics are exactly the same.  Let’s have a look.

 
Gains Are Lost – Projects Never Finish Early

Let’s take an extreme example where all of the tasks are completed in a shorter duration than the estimate.  The whole project should finish early – right?  If everything went swimmingly well then this is what we should achieve.

But have you ever seen this – in all honesty?  I suspect not, I certainly haven’t seen it.  The very best that we might expect to get is something more like the following.

We still have tasks completing in a shorter duration than the estimate – in fact we have a series of early finishes – but the next task doesn’t start until the scheduled start time.  The net effect is that the overall project hardly finishes early at all.

The reasons that we don’t get early starts to tasks and therefore early completions of the whole project are manifold.  Some are mechanical, some are psychological (and real rather than imagined).  Let’s have a look at the mechanical aspects first.

There is a dependency wherever there is a hand-off.  And I guess that we have made an inherent assumption here that each and every task utilizes different resources (also known as people).  In Critical Path Method, the Gantt chart functions as a schedule – that is it’s purpose after all.  So if there is an early completion of task 1, what is the chance that the resource assigned to task 2 can drop everything and begin an early start to task 2?  I would suggest that the chance is slim in the extreme.  The chance is slim in the extreme because the resource for task 2 didn’t expect it, certainly didn’t plan for it, and in all probability has a number of other tasks (both project and non-project) that are more important and probably running late in any case.  Thus even if preceding tasks are completed early, it is unlikely that the gains will be accumulated for use further on in the project.

If those are the mechanical reasons (essentially people are busy), what are the psychological reasons?  The psychological reasons belong more with the early finish of the preceding task rather than the early start of the succeeding task.  Ask yourself; how often have you seen a task finish early?  Probably not very often.  Note, I didn’t say ask how often they do finish early, I asked how often do you actually see it.  You don’t see it because it is hidden.  It is hidden for a number reasons.  In reality we see the following.

Even when individual tasks are essentially completed ahead of time and the duration is shorter then expected, the task will still appear to be completed at about the expected time.  Goldratt attributes this to polishing the tasks (2), known more commonly as Parkinson’s Law (3).  The additional time available until the actual completion date is used to “polish” the existing work to a higher standard, or the job can be slowed down as necessary.

Why would people choose to slow down their task rather than to complete it early?  One sound reason would be to protect the very valuable safety time that has been so hard fought for and won on previous occasions and which painful experience tell us that we need more often than we don’t need.  To lose that safety now would put further tasks in future projects in jeopardy and that is not something people wish to do at all.

The combination of successor task resources not being ready to start early when there is an early finish, and predecessor task resources not being willing to jeopardize future safety by finishing early ensures that gains in individual tasks are lost and that whole projects never finish early.  It sounds like a bold assertion, but I am willing to entertain any evidence to the contrary.

But this is only half the story.  We have only looked at the extreme of tasks that are shorter than the expected duration and thus have early finishes.  What about the other direction?  What about tasks that are longer than the expected duration or those that have late starts?  Let’s see.  It’s not nice.

 
Losses Are Gained – Projects Always Finish Late

We start once again with our simple project with our boringly uniform expected durations and 6 simple tasks

What would we expect to find if these expected task durations were each off-set by late starts?  Let’s have a look.

Consistent late starts of expected task durations will mean that the project as a whole will finish late.  Why would a task start late?  Again, there are mechanistic reasons and psychological reasons.  Let’s just deal with the mechanistic reasons first.  Ever heard of a task starting late because people were genuinely busy finishing a different task on a different project, or some non-project work that was important nevertheless to the overall business?  Of course you have.  In fact, such “legitimate” reasons might even see the late start recorded as such – a kind of badge of honor; “we would have started on time if we could have, but we couldn’t because we were busy.”

How about less legitimate reasons?  Well, like the early finish, we are unlikely to see such late starts recorded.  Instead we are much more likely to see the following.

The task may start on time and take longer than expected; we become the passive victim of variation in the process.  However, the task might start late and take as long as expected and is hidden within the general task duration.  Goldratt puts such late starts down to “Student Syndrome” (4).  This is more of a psychological effect than a mechanistic effect.  You see, some of us procrastinate.  If you can find the time, procrastination is sort of like a luxury.  And sometimes people are just so plum tuckered out that they need a “break” between tasks if they are to function effectively.  But you know, we can only afford to procrastinate when we detect that there is some slop in the schedule; we only procrastinate when we feel sure that there is sufficient safety ahead (if not in our task then in somebody else’s).  We only procrastinate when we are sure that our actions won’t put the whole project in danger.  Indeed, we might choose to procrastinate to protect the safety that we have fought so hard for and won in the past and which painful experience tells us that we need more often than not.  To lose that safety would put further tasks in future projects in jeopardy and that is not something we wish to do at all.

Its a sobering effect.  We are just trying to do our best, and yet it seems that at best our gains in individual tasks are lost and whole projects will never finish early and at worst losses in individual tasks are gained and whole projects will always finish late.

Why do we put up with this state of affairs?

As we saw earlier, shorter than estimated tasks can average out longer than estimated tasks, and for that matter early finishes can average out late starts as well.  However, for a number of mechanistic and psychological reasons this fails to happen.  It fails to happen because safety is embedded in each local task.  If for any reason we fail to utilize that safety it is lost to us for all time.  If only the safety was available in-totality somewhere to share out, rather than being embedded in each local task, then surely we could resolve the mechanistic problems and maybe some of the psychological ones too?  The only way to achieve this is to employ global buffering of the project.  There is another reason why we must employ global buffering, an issue that so far we have managed to avoid – uncertainty.

 
More Variability – Contingent Dependency And Uncertainty

So far we have only looked at dependency in terms of how the completion of one task affects the start of the next task.  Successor tasks are not only dependent upon the completion of the predecessor tasks, they are also often contingent upon them.  That is, the nature of the successor task can not be fully determined until the uncertainty is resolved by the predecessor task.  This of course might only unveil further uncertainty in the current task which is yet to be quantified.

For example, a project that includes foundation earthworks might encounter more difficult ground or easier ground than prior testing had indicated.  Outdoor projects are often contingent upon the weather.  This must be factored in.  Any form of overhaul and maintenance project is contingent upon the condition of the equipment as found after stripping the equipment down.  While our local garage may be able to say “it will depend upon what we find,” project-sized operations must make a reasonable allowance for such things ahead of the fact.  Contingent dependency and therefore uncertainty are common factors in projects.

 
More Variability – Novelty And Uncertainty

What happens the first time a pharmaceutical company makes its first scaling-up experiments?  A new recipe that works perfectly in lab scale trials is moved for the first time to pre-production trials.  Sure the rigs are the same as all the other pre-production trials and yet there is novelty in the current mix.  The chemistry, the quantities, the order of mixing, the mixing itself, and the consequent “cooking” are all new.  Will the yield and the quality be sufficient?  If not, what needs to be changed, and if there is a change, how many more trials until we can bring the project to market?  Where there is novelty, there is uncertainty.  In fact, where there are unknowns, there is uncertainty.

There is one more major source of uncertainty.  Let’s have a look.

 
More Variability – Resource Availability And Uncertainty

In a single project environment resources may not be dedicated solely to the project tasks.  In many small businesses some people assigned to project tasks may also be assigned to other non-project tasks that must be fulfilled, such as day-to-day business or managerial functions.  Such a case is very common in smaller professional firms.  In many firms, both small and large, there may also be many concurrent fee-earning projects each with its own needs and priorities.  Some people assigned to project tasks may be assigned to multiple tasks in different projects (and some non-project ones as well).  This would not be an issue if each task could be carried out to completion before the next is started.  Reality is that staff must chop and change – multi-task – between different projects according to ever changing needs, priorities, and mis-synchronization.  In fact, like fire-fighting in production operations, we often laud such activity, even if it is to the detriment of the individuals concerned – they get worn out – and the projects themselves – they are always longer and later than we want.

Uncertainty is a dominant characteristic of project operations.

If we found that;

There is variability around what is known

Then we must conclude that;

There is uncertainty around what is unknown

Unknowns and the consequent uncertainty are a fact of life in project operations.  How do we accommodate such uncertainty?  As it turns out, rather well actually, lets see.

 
Touch Time And Uncertainty

Strange as it may seem, it is very hard to find a novice production operation; even a new firm on a “green fields” site that starts from scratch will endeavor to employ people who have prior experience in the field, especially the detail complexity of the specific endeavor.  Ditto, project operations.  We know uncertainty exists and we accommodate it by extending the duration of the individual tasks.  The more uncertain we are, the more likely we are to seek longer task durations.  The duration is weighed-up against prior experience.  Every task automatically compensates or accommodates the uncertainty into the task estimate.  The real issue, as with the case of simple variation, is the existence of dependencies, and the local locking in of the embedded safety.

 
Uncertainty And Dependent Events

Greater uncertainty simply compounds all the effects that we observed earlier due to dependency – either mechanistic or psychological; any gains from individual tasks are lost and projects simply don’t finish early.  Moreover, any losses in individual tasks are accumulated and projects finish later and later.  This need not happen.  There is more than adequate safety allocated and embedded into each of the individual tasks.

 
Safety & Task Duration Estimates

We started our discussion on variability and dependent events with a simple project where the under-runs and over-runs around an average task estimate cancelled one another out and the overall effect was that the project finished on time.  This was based in part on the notion that some sort of “normal” distribution is at work at the task duration level.

Let’s have a look at this.

We suggested that some individual tasks would be shorter than expected and some would be longer than expected.  But that they would average out against the expected value.

Let’s expand this out a little more, a few more extreme values at either end and some quantitative estimates as well.

We have added a few even shorter and a few even longer tasks.  If task estimates were distributed like this, then we would have a normal distribution.

Let’s have a look at this.

The values for the task duration are clustered symmetrically about a mid-point which in the dark recesses of my mind I recall is the coincidence of the mean, the mode, and the median.

Let’s add some values to this distribution.

Knowing what we know now about the interaction of psychological and mechanistic aspects of multiple tasks in multiple arms of a simple project, what value of percentage chance of completion would we give?  It certainly wouldn’t be 20% would it?  It certainly wouldn’t be 50% either?  In fact, for a nice normal distribution we might even accept 100% without too much bother.  Unfortunately, our bad habits in the project management world would make 100% an impossible task.  We have to accept something lower.  Let’s see why.

For all the reasons we have discussed before, we won’t see many shorter than expected task durations and we will see many more longer than expected task durations.  The impact of this is to skew the distribution towards the longer task completion times.  Let’s have a look.

Compared to our former normal task distribution, our real task distribution is skewed out towards longer completion times.  Let’s have a look at the chance of completion of various durations.

The chance of completion is of course also skewed out towards the longer durations – significantly so.  We might like to use 100% but that would be something like more than three times the 50% duration.  If we come in a bit to 80% then we find that even this is twice the duration of the 50% level.  People do make accurate assessments of the task duration, including safety, to take into account the variability and uncertainty inherent in the task.  The more uncertain the task, the longer the tail.

We embed the necessary safety within each and every individual task duration estimate.  However, because this safety is localized it is frequently wasted and our worst fears come true (again); the overall project will not be completed on time.  We view this as a vicious cycle of a never-ending need for greater and greater safety estimates within the task duration.

If we could make this localized safety accessible for any and all tasks within the project by using buffers, then we would actually need less safety overall and yet still finish on time.  We need to know how to access this safety, where to put it, and how much.  These are essentially our task and buffer sizing rules.  Let’s have a look.

 
Heuristics – Task & Buffer Sizing Rules

Buffer sizing for projects, as for production operations, is based upon a rule of thumb, a heuristic if that sounds better.  It is based upon a rule of thumb because this has been found to be thoroughly effective over a very wide range of scope and scale of project management – from the maintenance of jumbo sized commercial aircraft to the product development of the tiny hard drives in our computers (5).  Remember we are after effective and implementable solutions; we don’t want ineffective nor un-implementable solutions; the world is awash with those already.

Let’s have a look at the rule.

We take our initial project plan,

and we halve each task; half is task time, half is safety.

The rationale is that people will give something like an 80% estimate of completion time (4).  That is they will not be able to give a 100% completion time; the long tail makes that impossible.  Nor will they give a 50% completion time; we know in projects that such a time will never be met.  But an 80% estimate gives us a four out of five chance of completion within our estimate.  Enough to be safe but not so much as to be silly.  The belief is that an 80% completion time is at least two times the duration of the 50% completion time (4).  We don’t know the real shape or values of the distribution, but this is the rationale. 

By halving the task duration we bring it back to something around the 50% level.  Then we will further protect this with adequate buffers.  This is ample sufficiency as we will see.  The over-runs and under-runs around this estimate will average out due to the placement of the buffers.  Moreover, halving the task duration has an important psychological effect that must not be underestimated in its overall importance.  It stops the waste of unreported early finishes – because there is precious little time to waste – and it stops the procrastination that causes late starts – for the very same reason.

Some terminology.  This shortened task time has a number of names, it has been called the “trimmed task time” (4), “best estimate” or “50% probable” (6).  It is also referred to as the “50% estimate,” the “focused task time,” and the “reduced task time.”  Take your pick.

The reason that there is more than ample sufficiency for individual tasks even at the 50% estimate is  because we aggregate the other half of the task, our safety, at the end of the tasks were it is accessible to all of the preceding tasks.

Let’s show this.

You may recall, this is where we got up to earlier in our comparison between production operations and project operations.  It has taken a while to get back to here, there were a lot of things to learn.

Again, we have some new terminology.  The buffer on the critical chain was initially called the “project buffer” (4) and this terminology has continued to be used in a number of sources.  However, a second term is also in use, that of “completion buffer” (7).  Once again you can take your pick, however, here we will be using “completion buffers” because that is what we are buffering and it is good to constantly remind people on projects that the project will be completed within the completion buffer – the term is self-reinforcing.  The feeding chains that arise parallel to the critical chain are uniformly called “feeding buffers.”

It is probably better to keep the name “project buffer” as the name of the class, and “completion buffer” and “feeding buffer” as members of the class, just as buffers in production operations consist of drum buffers, assembly buffers, and shipping buffers.

Returning to the detail of our simple project above, once again we find that tasks 4 & 5 are pushed back and that this has increased the total length of the project.  However, this is just an intermediate step.  Because the local safety is now aggregated and located in just a few strategic places, it will be better utilized, and we need less in total than we had before.

The rule is that we need only half as much aggregated buffer as we did as prior non-aggregated safety.  Therefore we must halve the buffers (4).

Let’s see what this gives us.

Half of a half is a quarter, we save a quarter of our original project duration due to the aggregation and placement of our safety.  This is because savings that accrue from tasks that are completed in shorter than expected durations can be fully utilized by tasks that are completed over longer than expected durations.  Looking at it the other way, losses that occur from tasks that take longer than the expected duration can be won back by tasks that are completed in shorter than the expected duration.  Thus our new project can be delivered on-time, and within 3/4’s of the previous estimated duration.  The effective average task duration is 75% of the previous estimate, not 50% as might be deduced from the halving of the original task time.  There is more than enough safety embedded in existing projects; we don’t know that it is there.  This approach allows us to access it fully.

Looking at it another way, our new project duration is made up of 2/3rd’s task and 1/3rd buffer.  And this leads us to a more generic buffer sizing rule.  Regardless of the task sizing rule that is used, the buffers must be 50% of the task estimate.  The “completion buffer is 1/2 of the lead time of the (trimmed) project” (7).

Take care to note; we now have a sequence, not a schedule.  Tasks 1, 2, 3, 4, and 6 are squashed up on the left; this doesn’t mean each task is expected to be finished in the time allocated to each task, nor that each will start immediately after the preceding one.  Instead we still expect the normal range of variation that we have experienced up until now, but that that variation will be accommodated from the global buffers

It’s taken us a long time to get here but I hope that it was worth it.

Before we finish however, let’s work through a project using our new found knowledge.  Here is the project plan or sequence.  We have added a some numbers to make it a little more clear how the plan progresses.

Let’s have a look at our simple project then at the completion of task 1.  We’ve added a time line to show were we are; everything to the left of the time line is in the past, everything to the right is in the future. 

Tasks 1 and 4 both took 6 units of duration to complete, that means that a portion of the buffers in both arms haves been utilized by the tasks.  The task durations were longer than that indicated by the sequence that we drew and have used some “time” from the buffer to make up the difference.  This is what we would expect to happen.

Let’s step it out another step.

Tasks 2 and 5 are now completed and both tasks once again have utilized the buffers.  Indeed the whole upper arm of task 4 & 5 is completed, although it used the whole of its buffer, and its is now waiting for task 3 to be completed before task 6 can begin.

Do you see what we mean about a sequence.  This is not a schedule, we don’t know at this moment when task 6 for instance will begin, nor for that matter when it will be completed.

Let’s step it out once again.

Well, we had to have at least one short duration, and task 3 was it.  We completed it in less than our reduced duration.  We actually gained a day from the buffer and we are ready to start task 6.

Let’s see what happens at the end.

Task 6 took longer than any of the other tasks, but the total project came in ahead of the finish date.  It didn’t need to; we should have been quite happy to finish on-time.  That would still have been 25% sooner than the previous estimate.

Hopefully this simple sketch shows you the nature of the buffer; it is there to be consumed in some rough proportion to the tasks at hand.  Its location ensures that we can average out the over-runs and the under-runs.  By aggregating the safety we can be equally effective with less, and thus the whole project can be completed, not only on time, but also in less time than we might otherwise manage.  We are also dealing with a sequence rather than a schedule; the start and finish dates are fixed, but everything else is free to move as needed to accommodate the variation and uncertainty in the project as it unfolds.

Buffering of the project plan is just one aspect of Critical Chain Project Management.  We’ve labored it here, because there are so many subtleties that need to be explained.  It should be pointed out that strictly speaking we currently have a buffered Critical Path, and in the next section we will show the difference that converts it into a Critical Chain.  Also we have spent a lot of time on an aspect of project management which is essentially project planning.  The greatest gains from Critical Chain Project Management don’t come from the planning but rather from the execution.  Having a buffered Critical Chain plan, and knowing how to monitor the buffer against the plan gives project managers a degree of control that is unimaginable with Critical Path Method – as we shall see in the next page.

 
Summary

Most of the problems in project operations, like production operations, must be psychological – our competitors don’t seem to have undue inability to produce similar products/services and yet we all seem to have similar problems along the way.  Treating the problem as psychological and “of us” rather than “of them” helps us to more readily frame the solution.  To put it more bluntly, if nothing else works at least we should be open to changing our own thinking.  Recognizing the implicit embedded safety in each individual task and moving it to a more compact and globally accessible buffer is an important step along this path.

A project is an “A” plant tipped on its side.  Both project operation buffers and production operation buffers in Theory of Constraints are exactly the same animal.  The differences come from the fact that we ignore touch time in production applications and include it in project applications.

Project buffers allow us to aggregate system safety in a few critical places where it is available to all preceding tasks and thus allows the effective averaging out of tasks that take longer durations than expected with those that take shorter durations than expected.  Aggregated safety as global project buffers is in fact more than adequate compared to the case where safety is distributed locally and embedded within each task.  Therefore projects can be completed on-time and within 75% of the previous estimates.  However, there is more than just buffers to Critical Chain Project Management, and we must now turn our attention to these.

 
References

(1) Karl Buckridge, personal communication 2008.

(2) Goldratt, E. M., (1998) Project Management the TOC Way.  Avraham Y. Goldratt Institute Limited, pg 40.

(3) Newbold, R. C., (1998) Project management in the fast lane: applying the Theory of Constraints.  St. Lucie Press, pp 25-27.

(4) Goldratt, E. M., (1997) Critical chain.  North River Press, 246 pp.

(5) Kendall, G. I., (2005) Viable Vision: transforming total sales into net profits.  J. Ross Publishing, pg 79.

(6) Leach, L.P., (2000) Critical chain project management.  Artech House Inc., pg 110.

(7) Goldratt, E. M., (2003-2006) TOC insights into project management and engineering.  Goldratt’s Marketing Group (software-based tutorial).

This Webpage Copyright © 2008 - 2009 by Dr K. J. Youngman